Reconfigure the chart above into a critical path diagram for project scheduling similar to the diagram shown in this module’s lecture, homework help

In a 1-page Word document, consider the following activities and their durations. The original project schedule, using early activity starts, is shown below.

Activity Task Predecessors Duration Activity Cost
A Sign Contract None 5 days $5,000
B Design Survey A 3 days $1,500
C Identify Audience A 7 days $1,000
D Run Survey B, C 30 days $6,000
E Analyze Results D 5 days $3,000
F Create Presentation E 5 days $1,000
G Present to Client E, F 2 days $3,000
  • Reconfigure the chart above into a critical path diagram for project scheduling similar to the diagram shown in this module’s lecture.
  • What is the duration of the project?
  • How much slack is currently available in the non-critical path?
  • How long are the project and feeder buffers?
 
"Looking for a Similar Assignment? Order now and Get 10% Discount! Use Code "GET10" in your order"

If this is not the paper you were searching for, you can order your 100% plagiarism free, professional written paper now!

Order Now Just Browsing

All of our assignments are originally produced, unique, and free of plagiarism.

Free Revisions Plagiarism Free 24x7 Support