Crashing and Earned Value Problems

In this homework assignment, you will be working through two crashing problems and four earned value problems. All the information you need is included within this Homework packet. Make sure you answer all parts of the questions in their entirety.

Once you have worked through the problems, please post your responses to the Dropbox. Please refer to the course Syllabus for the due date.

PROBLEM 1

Use the network diagram below and the additional information provided to answer the corresponding questions. (15 points)

a) Give the crash cost per day per activity. (10 points)

b) Which activities should be crashed to meet a project deadline of 10 days at minimum cost? What is the cost impact of crashing these activities? (3 points)

c) Find the new budget (or cost of the project). (2 points)

PROBLEM 2

Use the network diagram below and the additional information provided to answer the corresponding questions. (13 points)

a) Give the crash cost per day per activity. (10 points)

b) Which activities should be crashed to meet a project deadline of 13 days at minimum cost? What is the cost impact of crashing these activities? (3 points)

PROBLEM 3 (8 points)

Month AC PV EV
22 $540 $523 $535

a)         Calculate the cost variance (CV). (2 points)

b)         Is the CV over or under budget? (2 points)

c)         Calculate the schedule variance (SV). (2 points)

d)         Is the SV ahead of or behind schedule? (2 points)

PROBLEM 4 (8 points)

Month AC PV EV
5 $34 $42 $39

a)         Calculate the cost performance index (CPI). (2 points)

b)         Is the project cost efficient or not efficient? (2 points)

c)         Calculate the schedule performance index (SPI). (2 points)

d)         Is the schedule efficient or not efficient? (2 points)

PROBLEM 5 (8 points)

Day AC PV EV
65 $550 $735 $678

a)         Calculate the cost variance (CV). (2 points)

b)         Calculate the cost performance index (CPI). (2 points)

c)         Calculate the schedule variance (SV). (2 points)

d)         Calculate the schedule performance index (SPI). (2 points)

e)         Given these data, what should a project manager do with respect to this project?

PROBLEM 6 (8 points)

Day AC PV EV
65 $760 $735 $678

a)         Calculate the cost variance (CV). (1 point)

b)         Calculate the cost performance index (CPI). (1 point)

c)         Calculate the schedule variance (SV). (1 point)

d)         Calculate the schedule performance index (SPI). (1 point)

e)         Explain the project performance in terms of efficiency, budget, and schedule. What should the project manager do for the project? (4 points)

 
"Looking for a Similar Assignment? Order now and Get 10% Discount! Use Code "GET10" in your order"

If this is not the paper you were searching for, you can order your 100% plagiarism free, professional written paper now!

Order Now Just Browsing

All of our assignments are originally produced, unique, and free of plagiarism.

Free Revisions Plagiarism Free 24x7 Support