Update the following microsoft profile that is attached according to bullet points in description, management homework help
Update the following
- Allocation of resources to project tasks (both labor and material), shown as resource assignments in the Microsoft® Project file (1 hr.)
- Cost estimates for project resources, entered into the resources information portion of the Microsoft® Project file (hr 0.5)
- Develop a baseline for your project plan so that all future variances are captured. (hr 0.5)
In addition, write a 1-page summary document explaining any relevant facts about the project duration, number or type of resources, critical task sequencing, or how duration estimates were arrived at, and any financial implications (for example, budget or cost reports of the project as well).