CPM

Session 9 IA-9(1)

Given the network plan that follows, compute the early, late, and slack times answer the following:

1. What is the project duration?

2. Using any approach you wish (e.g., trial and error) develop a loading chart for resource resources Carpenters (C) and Electricians (E). Assume only one Carpenter is available and two Electricians are available. 

3. Given your resource schedule, compute the early, late, and slack times for your project.

4. Which activities are now critical? 

5. What is the project duration now?

Use the templates provided below to construct your charts/tables.


ANSWER:  

          2       4          
          C       E          
0 1       3       3       6  
  C                       C  
  3       3       5       2  
          C       2-E          
          1       4          

ANSWER:

Carpenter                            
                             
Electrician                            
    0 1 2 3 4 5 6 7 8 9 10 11 12 13
                               

  ANSWER:

ID/RES ES LS EF LF SL
1-C          
2-C          
3-C          
4-E          
5-2-E          
6-C          
 
"Looking for a Similar Assignment? Order now and Get 10% Discount! Use Code "GET10" in your order"

If this is not the paper you were searching for, you can order your 100% plagiarism free, professional written paper now!

Order Now Just Browsing

All of our assignments are originally produced, unique, and free of plagiarism.

Free Revisions Plagiarism Free 24x7 Support